Final assembly of the LOHC reactor rack in Erlangen

Preparations for the LOHC-One reactor, e.g. for the delivery of its parts and for assembly at the planned site in Jülich are in full swing. Final assembly of the reactor rack has now been successfully completed in Erlangen.

Delivery of the individual components is expected to take place in Q1 / 2024 t. Once the components have been assembled - beginning in April/May 2024, the reactor can then hopefully go into test operation from end-2024 / early 2025.

For more information on LOHC research, click here.

Last Modified: 08.12.2023